Top 50 Homebuilder. The build that proved the system.

Top 50 Homebuilder had invested heavily in an ERP implementation — Oracle JD Edwards — that never got adopted. Three years in, their estimating team was still running Excel, their sales selections lived in email, and there was no connection between what a buyer chose and what got ordered.

We didn't replace the ERP. We built the layer the ERP was missing — a sales configurator that connected every upstream selection to every downstream system, with no manual steps in between.

14 days → 48 hrs
Sales-to-purchase order cycle, before and after the Configurator integration.

The numbers

MetricBeforeAfter
ERP adoption 38% 94%
Sales-to-purchase order cycle 14 days 48 hours
Manual data re-entry steps 11 steps 0
Option pricing errors ~8 / month 0
Takeoff turnaround 3–5 days Auto on sale
Annual tech waste eliminated (Year 1) $94,000